Conversion of Ashtart PF2 Platform Crane Pedestal into Diesel Storage Tank
Owner SEREPT, Tunisia
Our Scope
Our Scope
- Calculation of the forces and moments on the tank/crane pedestal as per API Specification 2C.
- Finite Element Modeling (FEM) and Analysis of the tank shell/crane pedestal.
- Finite Element Analysis (FEA) of the crane pedestal.
- Deterministic fatigue life of the pedestal and supports.
- ASME VIII DIV 1 calculations of tank bottom and nozzles.
- ASME VIII DIV 1 calculations of tank shell, nozzles and manways.
- ASME VIII DIV 1 calculations of tank roof.
- Tank general arrangement and detailed drawings.
- Mechanical data sheet of the modified tank.
- Tank vent sizing calculations as per API 2000.
- Cathodic protection design calculations for the tank internal surface.
- Specification of internal coating of all tank internal surfaces.
- Inspection and Test Plan (ITP).
- Definition of the required Non-Destructive Tests (NDT) type and extent.
- Assisting SEREPT up to the entire certification by third party of the mechanical detailed engineering SoW deliverables.
Risk Assessment, Fitness for Service and Repair Study for Crude Oil Storage Tank 70T1
Client Maretap
Location Tunisia Description Provided fitness for service assessment according to API 650, 653 and 579 for 54 m diameter atmospheric crude oil tank with 200,000 Barrels capacity.
|
Engineering for Hydrocarbon Storage Tank Farm
Owner TANKMED, Tunisia
Contractor SOCOMENIN (IET), Tunisia
Our Scope
Contractor SOCOMENIN (IET), Tunisia
Our Scope
- Design of 5 fixed cone roof Hydrocarbon Tanks with total capacity of 104,600 cubic meters including issuance of detailed design calculations and fabrication drawings in accordance with API 650.
- Piping stress analysis for tank farm piping including buried piping and issuance pipe supports detailed drawings.
EPC Tender package 2010-5 (Piping Works for LPG tanks T601, T602, T603 and Gasoil tanks T112, T501, T502)Owner SONKER Oil Tanking Company (SOTCO)
Consultant CB&I Contractor Integrated Engineering Group (IEG), Egypt Our Scope We acted as the Engineering arm for the Contractor, taking the responsibility for Preliminary engineering works, FEED verification, engineering clarifications meetings with the Owner and material cost estimate. |
Engineering Verification and Techno Economic Study for Crude Oil Tanks retrofit to handle Fuel Oil
Owner SUMED
Location Ain Sokhna, Egypt
Our Scope
Location Ain Sokhna, Egypt
Our Scope
- Engineering verification and calculations for 4 existing floating roof crude oil tanks to check that they fit for the purpose of handling fuel oil instead of crude oil.
- Conceptual design including process simulation and sizing of fired heaters, centrifugal pumps and pipeline.
- Techno-economical study and cost estimate for the Engineering Procurement and Construction and Management (EPCM) works.
Detail Engineering and Design Calculations for 18 Pressure VesselsOwner British Gas, Tunisia (Hasdrubal Gas Treatment Project)
Main Contractor Petrofac Fabricator SOCOMENIN, Tunisia Our Scope Detailed design calculations and fabrication drawings for 18 pressure vessels in accordance with ASME VIII DIV. 1 |
Assessment and Solution of Pipework vibration Problems
Client International Oil and Gas Operator
Location North Sea
Description
Location North Sea
Description
- Conducted velocity-vs-frequency measurements of vibrating features to assess the criticality of the vibrations as per the UK Energy Institute Guidelines for the Avoidance of Vibration Induced Fatigue Failures (AVIFF).
- Conducted strain gauge measurements to calculate the stresses and remaining fatigue life for the vibration features that exceeded the AVIFF concern and problem zone criteria.
- Conducted surface crack detection examination to check for any vibration induced cracks for the features that exceeded the AVIFF concern and problem zone criteria to ensure that they are safe to remain in service until the required pipework modifications are implemented.
- Specified the required pipework/pipe support modifications to mitigate the vibration problems.
- Conducted CAESAR II piping stress analysis to assess the impact of the pipework modifications on the stress and flexibility of the pipework.
Piping Repairs Using Engineered Composite Wraps Designed to ISO 24817 or ASME PCC-2
Client International Oil and Gas Operator
Location North Sea Description We consider the following in the design and construction of Engineered Composite Wraps:
|
Risk-Based Inspection (RBI) for Corrosion Under Insulation (CUI)
|
Disclaimer
We present here our key projects, some of which are executed under Technical Integrity Solutions Ltd. name and others were executed by us before establishing Technical Integrity Solutions Ltd.
We present here our key projects, some of which are executed under Technical Integrity Solutions Ltd. name and others were executed by us before establishing Technical Integrity Solutions Ltd.